Wednesday, November 25, 2009

Roof

Progress has really been hampered in the past while with all the rainfall and storms.

Some of the slabbing has started, but it still limited as to where it can go as the house is not fully watertight yet. First fix electrics has been done in the rooms upstairs.

Our temporary staircase ...
Plastering of the chimneys has finally started, so the roofers can slate more.

Tuesday, November 17, 2009

Roof ongoing




So much happening at the moment. Windows have been prepared and protected for the plastering. The slates have arrived and they are starting to put them up this week. The bases for the solar panels have been installed. The insulation is going in the attic and the walls have been chased for the electricians arrival tomorrow.

Friday, November 6, 2009

Wednesday, November 4, 2009

Windows, Doors and roof

Front of house - starting to take shape!
View from the drive in.
Side door into the utility
Back of the house - double doors into the play room.

Sunday, November 1, 2009

Windows

The windows and french doors went in last Friday - don't have any photos yet as the weather is so crap - hopefully will have some up later this week.