Finished Floor


The finished ground floor was poured and polished today.


Blocks should start later this week. Can't wait to see the walls going up.

Friday, July 17, 2009

Sub floor levels.


The radon barrier has been installed (above) - to protect us from that horrible gas - even though apparently you don't need it with a raft foundation, but regulations still demand it!


The floor insulation has been installed and also the ground floor plumbing - so many decisions so far - where do you want this sink, what size radiator, where is the washing machine going .. so many decisions already - and I am sure so many mistakes made already :-)


With the blocks at edges, you can finally make out each room and their sizes. Can't believe so much has happened in the past week.




The garage is being prepared in the background - hopefully that will be poured next week - but knowing our builder, I could get a suprise if I go out there tomorrow!!

Tuesday, July 14, 2009

Foundations being poured

As always - click on the pictures to see them in full size.




Concrete finally being poured for our foundations. Can't believe there is so much steel needed in the foundations. No chance of this house ever moving!!!
The two pipes sticking up in the middle are for the bathroom waste.

Saturday, July 11, 2009

Going up finally instead of down!

The hardcore has gone in and the site is finally looking like a building site!




These are mounds of hardcore - the steel will be going in the gaps between them to support the concrete first floor and house.





This is the outline showing the front porch.


This will be the view from the double doors in our kitchen/dining room.


The shuttering around the house outline has been done and the steel is finally going in for the concrete pour. I will upload some photos if the weather improves!!